
Oak Ridge Y-12 plant
Date Established: 1942
Present Mission: Weapon component dismantlement; special nuclear
material (SNM) storage; maintenance of technical capability for weapons
development and production, stockpile maintenance and evaluation, and
nonproliferation and arms control; technology transfer.
Size: 811 acres
Employees: 4000 as of July 29, 1996, representing a reduction from
6,388 as of September 30, 1994.
Annual Budget: The total fiscal year (FY) 1998 estimated site
budget is: $469.8M for FY 1996, $482.1M for FY 1997, $612.8M for FY 1998.
Cognizant Secretarial
Officer: Assistant Secretary for Defense Programs (DP); principal DP
offices include DP-20, Deputy Assistant Secretary for Military Application
and Stockpile Management, and DP-24, Office of Site Operations.
Responsible Operations/Area Office: Department of Energy (DOE) Oak
Ridge Operations Office (OR)/Y-12 Site Office (YSO).
Management and Operating Contractor: Lockheed Martin Energy
Systems (LMES).
Fissile Material: 171.9 metric tons of enriched uranium; other SNM
(December 1993)
The Oak Ridge Y-12 Plant
is situated at the eastern end of the Oak Ridge Reservation, adjacent to the
city of Oak Ridge, in Anderson County, Tennessee. The plant, consisting of
531 buildings containing over 7,000,000 square feet of space, occupies an
area approximately 0.67 mile wide and 3.2 miles long.
Y-12 was originally constructed in 1943 as part of the Manhattan Project.
Its initial mission was the separation of fissionable isotopes of uranium
(U-235) by the electromagnetic process. Built in a rural section of East
Tennessee, the Y-12 National Security Complex, previously known as the Oak
Ridge Y-12 Plant, was part of the Manhattan Project. Its job was to process
uranium for the first atomic bomb. Construction of Y-12 started in February
1943; enriched uranium production started in November of the same year.
Construction, however, was not entirely finished until 1945. At its peak
during the war, Y-12 employed 22,000 workers. The first site mission was the
separation of uranium-235 from natural uranium by the electromagnetic
separation process. The magnetic separators were taken out of commission at
the end of 1946 when gaseous diffusion became the accepted process for
enriching uranium.

Since World War II, the number of buildings at Y-12 has doubled. Today,
the Department of Energy’s Y-12 National Security Complex is a manufacturing
facility that stretches over 811 acres. Its 250 buildings contain about 7
million square feet of floor space (the square footage of 150 football
fields). Its mission and capabilities have changed as well. Over the ensuing
years, Y-12 has become a highly sophisticated nuclear weapons component
manufacturing and development engineering organization.
The mission at Y-12 changed at the end of the Cold War from producing
nuclear weapon components to maintaining the capability to produce
secondaries and cases (capability assurance). Current Y-12 missions include
receipt, storage, and protection of uranium and lithium materials and parts;
directive work (process technology and development support); stockpile
surveillance (quality evaluation); material recycle/recovery; and
dismantlement capability and facility transition.
Y-12 core stockpile management (CSM) missions support the maintenance and
evaluation of the stockpile through manufacturing, process technology, and
development assistance. The site continues to move to a consolidated and
downsized Defense Programs reduction footprint.
The President and the Congress have directed the Department of Energy
(DOE) to maintain the safety and reliability of the nation’s nuclear
deterrent without underground nuclear testing. In order to do that, DOE has
established a program of science-based stockpile stewardship. Y-12 is an
integral part of that mission. Stockpile stewardship refers to the
activities associated with research, design, development and testing of
nuclear weapons and the assessment and certification of their safety and
reliability. Stockpile management refers to the activities associated with
production, maintenance, surveillance, refurbishment and dismantlement of
the nuclear weapons stockpile.
Nuclear manufacturing includes the manufacture or remanufacture of unique
nuclear weapon components for the nation’s long-term defense capabilties.
Precision fabrication services are supported by mature management and
safeguards systems. Nuclear manufacturing includes Depleted and Enriched
Uranium Operations; Special Materials Operations; and the Assembly,
Disassembly, and Storage Operations, all in support of the nation’s nuclear
stockpile.
Weapon dismantlement, storage and evaluation includes primarily the
disassembly of returned weapons components and quality evaluation for the
existing weapons stockpile with surveillance of weapons through disassembly
inspection and documentation of findings. Minimum processing is used to
reach a state of safe, secure, legally compliant, and economical storage of
the materials.
Y-12’s focus on national security ensures safe operation and management
of Y-12, the nation's “Fort Knox” of highly enriched uranium, the leader in
uranium and lithium materials research, development and processing and the
country’s assembly and disassembly plant for nuclear weapon secondary
components. This national security focus ensures comprehensive support for
Y-12 non-proliferation and international nuclear materials safeguard
programs. This office provides support to DOE in the development and
monitoring of arms control and nonproliferation. The group also provides
support for implementation and operates the Nuclear Materials Management and
Safeguards System.
Enriched uranium material warehousing and management oversees the secure
management and storage of special nuclear materials as weapons are retired
from the national stockpile or returned for dismantlement under strategic
arms reduction treaties. This function also includes the management and
storage of nuclear materials that are returned to Y-12 from other DOE sites,
including DOE-owned nuclear material from universities and other research
facilities, both domestically and internationally. This work also includes
the processing of enriched uranium for various applications, including
enriched uranium processing and storage for DOE’s Central Scrap Management
Office.
Y-12 supports DOE’s stockpile management program by maintaining the
reliability and safety of weapons in lieu of underground testing and
providing resources to address safety, programmatic and operational
considerations, including maintaining the required technology, critical
skills and physical assets for weapon production. As with all other
missions, protecting the public, workers and the environment is a priority
when Y-12 activities are performed.
The Oak Ridge Operations Office (OR) is responsible for managing and
overseeing operations of all facilities under its jurisdiction. The three
largest sites are located in Oak Ridge, Tennessee: the Oak Ridge National
Laboratory (ORNL), Y-12, and K-25. OR continues to maintain a presence at
Paducah and Portsmouth Gaseous Diffusion Plants primarily for environmental
remediation and waste management.
OR has delegated all day-to-day operational functions of ORNL, Y-12, and
K-25 to the Department of Energy (DOE) site offices, headed by a site office
manager and associated support staff, except for day-to-day environment,
safety, and health (ES&H) functions at ORNL and K-25. These are performed by
the OR matrix organization. The staff at the site offices are considered a
line function, and report through the site office manager to the appropriate
OR assistant manager (Defense Programs, Energy Research, Environmental
Management, or Uranium Enrichment Operations).
The OR Manager is the Contracting Officer for all OR projects. The site
office managers are designated as Contracting Officer's Representatives for
most of the projects at their sites, except those administered directly by
OR or another line function. For example, the DOE Y-12 Site Manager is
responsible for all day-to-day production/operation related activities at
Y-12 but is not responsible for environmental restoration and waste
management activities, which are managed by the Assistant Manager for
Environmental Management. Neither are the site office managers responsible
for contracts managed by other elements of OR, such as the Oak Ridge
Federal/Integrated Communications Network (ORF/ICN), which is managed by
OR's Information Resources Management Division.
Y-12 and K-25 sites are operated by Lockheed Martin Energy Systems (LMES).
LMES has created a structure similar to OR and assigned day-to-day
plant-level operations to each site's management chain. LMES has retained
certain functions at its corporate office, such as administering large
subcontracts than operate at more than one site. For example, the M. K.
Ferguson-Oak Ridge Company, managed by LMES, is the Construction Manager for
all major OR sites.
OR also administers other contracts for the Oak Ridge Reservation,
including the contract with Johnson Control, Inc. for management of the Oak
Ridge Water Treatment Plant and maintenance of roads and grounds; U.S. West
for ORF/ICN; Bechtel National Corporation for environmental remediation and
demonstration projects; and Jacob Engineering and Lockwood Greene for
architect/engineering services. OR has recently begun a contracting process
whereby specialized services are contracted and managed by LMES or others.
These projects are also considered outside the normal scope of the DOE site
offices responsibilities.
Recent staff realignments within OR have resulted in the matrixing of
most support staff functions to the three OR sites. For example, most of the
technical staff within the OR Safety and Health Division have either been
reassigned to one of the three OR sites or transferred to support
organization within OR's Environmental Protection Division. It is unclear at
this time how OR will discharge responsibilities for conducting
multifunctional appraisals, special reviews, and other processes previously
assigned to the Safety and Health Division.
OR manages the activities at Y-12 and established the Y-12 Site Office (YSO)
to oversee contractor activities at the Plant. YSO has about 35 employees
who report to the YSO Manager, who reports to the OR Manager through the
Assistant Manager for Defense Programs.
OR has 660 full time equivalent (FTE) staff. With strategic realignment
of DOE, OR will lose 55 FTEs in the next two years and 100 FTEs over the
next five years. It is not clear how many FTEs will be lost at YSO.
LMES announced the next phase of workforce downsizing on August 26, 1996.
The total downsizing announced by OR in May 1995 is estimated to total 900
LMES jobs by the end of fiscal year (FY) 1996. These reductions are in
anticipation of lower budgets in FY 1997 as well as completion of previously
funded projects, restructuring, and reorganization.
LMES is the integrating contractor. LMES (or its predecessor
organization) has operated Y-12 since 1984. The LMES contract was due to
expire in March 1996; however, an extension through March 1998 was
authorized in 1995. (This contract extension required that ORNL be placed
under a separate contract, which was negotiated with a new entity, Lockheed
Martin Energy Research Corp., effective January 1996 and extending through
March 1998.) A new performance-based management contract was negotiated and
signed with LMES in August 1995, effective October 1995 through March 1998.
This new contract incorporated all of the major elements of the Department=s
contract reform initiative: providing objective vs. subjective performance
measures, establishing performance incentives through multiple fee
arrangements, emphasizing and providing incentive for cost reduction,
shifting of risk and liability to the contractor. On August 6, 1996, the
Department announced its decision to extend the contract with LMES for the
operation of the Y-12 Plant for two years, through March 2000. The primary
reason for this decision is to avoid any disruption of some critical
Department of Defense requirements.
Production activities at Y-12 were placed in a stand down mode on
September 22, 1994, due to procedural and criticality safety concerns
identified by the Defense Nuclear Safety Board. Since then, Y-12 has made
progress improving its operations throughout the plant. Selected crucial
operations were performed in these areas under control of a special
operations package. Defense Nuclear Facilities Safety Board (DNFSB)
Recommendation 94-4, "Deficiencies in Criticality Safety at Oak Ridge Y-12
Plant," provides a detailed background of these conduct of operations
problems.
Briefly, a DNFSB staff member identified a nuclear criticality safety
infraction at Y-12 in September 1994. Because of improper management
response to the infraction, Y-12 operations were placed in stand-down. In
the days following the stand-down, hundreds of similar nuclear criticality
safety deficiencies were identified at the Plant and at the other DOE sites
in Oak Ridge. As a result, the stand-down was continued for most of the
plant nuclear operations. Operations in Y-12 facilities have been resumed in
phases. Some have already begun, such as the warehousing and shipping, and
the assembly and disassembly operations.
Since the stand down, Y-12 personnel have worked to restart operations in
the following mission areas: Receipt and Shipment, Disassembly and Storage
Operations, Depleted Uranium Operations, and Stockpile Surveillance, while
continuing to meet defense mission requirements. On June 8, 1998 Y-12
resumed the last of its production missions, Enriched Uranium Operations,
when it cast its first enriched uranium part since September, 1994. Y-12 is
currently involved in the life extension program for the Peacekeeper Missile
warhead, called the W87. Initial delivery of key components of this weapon
are due at the end of 1998, and manufacturing will continue for several
years.
KEY FACILITIES
The Y-12 National Security Complex has been making nuclear components for
the U.S. Department of Energy (DOE) since 1944. Facilities have become
increasingly more expensive to maintain as the aging structures become
outdated and require extensive repairs. In comparing the current method of
repeated repair and maintenance with the option of constructing new,
state-of-the-art facilities, it has been determined that the mission of
National Security will be best supported through the development of new,
technologically superior facilities.
In 1998, DOE Oak Ridge Operations (ORO) officials announced that a
uranium storage building, called the Highly Enriched Uranium (HEU) Materials
Facility, would be built as the first segment of a project to upgrade and
modernize Y-12’s aging equipment and structures. DOE-ORO’s plans are to
include money to begin construction on the HEU facility in the federal
budget in fiscal year 2001. The plan is to build the rest of the new uranium
process facilities in phases which could extend to the year 2015. After the
initial facility is built, construction work would begin on a new uranium
manufacturing center.
Additional work will include process buildings along with infrastructure
and utility improvements. A site-wide Environmental Impact Statement is
under way in preparation for the construction and demolition that will take
place with the modernization effort.
Building 9201-4, Alpha 4
This nuclear facility, constructed in 1945, was originally used for
electromagnetic separation of uranium. It was later used for separation of
lithium isotopes. It occupies 562,000 square feet of space, is shut down,
and is assigned to EM. However, all major Y-12 plant utilities run through
this facility, and it is the hub of the entire electrical system of Y-12.
The building contains large quantities of mercury and other hazardous
materials, such as asbestos, lithium, lithium hydroxide, and mixed wastes.
Although this facility is deteriorating, it is still in good condition.
About 50 to 70 workers occupy this building, and extensive precautions are
take to protect the workers from the risk of exposure to the hazardous
materials.
Building 9201-5, Alpha 5
This building was constructed in 1945 and occupies 591,500 square feet of
space. The primary mission of this facility is to process and manufacture
depleted uranium and non-uranium materials parts. In addition, beryllium,
lithium, and depleted uranium in various forms are stored in this facility.
Combustibles contaminated with enriched uranium are also stored in 9201-5.
There are plans to relocated the arc melting operation to the 9998 H-1
foundry.
Building 9201-5N/5W, Alpha 5N/5W
This nuclear facility, constructed in 1972 and occupying approximately
80,500 square feet of space, is used to machine depleted uranium. There is
some risk of depleted uranium exposure or uptake to workers in this
facility.
Building 9204-2, Beta 2
This building was constructed in 1954 and occupies 270,000 square feet of
space. The primary mission of this facility is to manufacture non-nuclear
components for weapon production. This mission includes salvage and recycle
of weapon components made from lithium hydride and lithium deuteride and
storage of these and other lithium-based materials for possible reuse.
Today's lithium operations are generally industrial types: non-nuclear,
non-radiological, chemical, foundry, and metal working processes. Much of
the original equipment has been replaced or upgraded by the lithium process
replacement project and other projects since the late 1980s with significant
improvements in safety, waste minimization, and process control.
Building 9204-2E, Beta 2E
This facility occupies approximately 151,200 square feet of space and was
constructed in 1969. It is currently used for: (1) processing cleaning,
assembling, welding, and preparing nuclear components for shipment; (2)
disassembling, storing, and preparing non-nuclear components for shipment;
(3) dismantlement,; and (4) quality evaluation and component certification.
Operations resumed in March 1996. A major hazard is the significant
quantities of special nuclear material (SNM). While the risks are relatively
low, the workers are exposed to radiological and industrial hazard and to
possible nuclear criticality. Significant events include failure to comply
with fire protection system surveillance requirements and operational safety
requirements (OSRs).
Building 9204-4, Beta 4
This nuclear facility, constructed in 1949, occupies approximately
273,000 square feet. It is used for disassembly, testing, and storage of
warhead components produced at Y-12. Portions of this facility have become
active as part of receipt, storage, and shipping (RSS) operations. Other
activities, such as quality evaluation (QE), are being performed under
special operation packages. The mission of this facility is being moved to
Building 9204-2E; the move is scheduled to be completed by 2002. In
addition, depleted uranium and non-uranium metals are processed in this
facility. Plans are to relocate this activity to Buildings 9212, 9996, and
9998. A major hazard is the presence of significant quantities of SNM and
hazardous substances; while the risks are relatively low, workers are
exposed to hazardous substances and to possible nuclear criticality. A past
significant event includes violation of OSRs.
Building 9206
This nuclear facility, constructed in 1946, occupies approximately 67,294
square feet. It was used to recover enriched uranium from scrap and trash.
However, it is in stand-down with limited operations, due to conduct of
operations concerns identified by the DNFSB. A major hazard is the presence
of significant quantities of SNM and hazardous substances. While the risks
are relatively low, the workers are exposed to hazardous substances and to
possible nuclear criticality. A past significant event was failure to
conduct monthly inspection required by criticality safety approval, which
constitutes a violation of OSRs.
Building 9212 Complex
This facility was built in 1949 and occupies approximately 311,325 sq.
ft. and is used for recovery, purification, and processing of enriched
uranium into usable products or forms suitable for storage. The major
hazards are nuclear, radiological, and hazardous chemicals present in the
facility, and standard industrial hazards. Significant events are: 1) the
required annual test of the baghouse Halon system did not test all required
components; 2) CSA requirements were not strictly enforced; and 3) there was
uptake of radiological material by workers. An internal investigation by the
contractor resulted in a detailed report that identified the causes of the
uptake and the recommendations to prevent a recurrence. The uptake resulted
in a committed effective dose equivalent of # 5 mrem for all of the attested
workers. The Price-Anderson Amendment Act audit conducted in October 1996
focused on this event. The results of the audit are pending. The facility is
in stand-down with limited operations due to conduct of operations concerns.
Building 9215 Complex
This nuclear facility was constructed in 1950 and occupies approximately
157,000 square feet of space. It was used to manufacture parts for depleted
and enriched uranium. Portions of this facility has become active as part of
RSS operations. The remainder will be reactivated as part of the enriched
uranium operations restart. The major hazard is the presence of significant
quantities of enriched and depleted uranium.
Building 9720-5
This nuclear facility was constructed in 1945 and occupies approximately
53,949 square feet of space. It is used for storing enriched uranium weapons
parts, assemblies, and other SNM for Y-12. The major hazard is a significant
quantity of SNM. A significant event is failure to comply with fire
protection system surveillance requirements, which is a violation of OSRs.
Building 9995
This nuclear facility was constructed in 1952 and occupies approximately
84,000 square feet of space. It is an analytical laboratory used, among
other tasks, to assay nuclear components. This facility was maintained as a
continuing operation. |