redline:
I've been to one plant that trained in the afternoon until about 22:00 that was nice since I was going to night shift. It's tough on the training staff though, they cant work all day and all night.
Henry, you're right about schedules even within the same utility, but, it's all about money and whether or not the company is is buying or selling. Having two units down at one time in March is often more cost effective than having one unit down in May.
If I were thirty years younger I'd say bring back those 120 day outages where we worked 6-7 12's....but since I aint so young any more, I say let's quit doing outages all together and go do some routines! Two outages next year...that blows!