--- Quote ---The day before Georgia Power’s headline stealing news, staff and the independent construction monitor filed testimony at the Georgia Public Service Commission covering the latest six months of activity at the site (from July 2016-December 2016, with rollover analysis through April 2017). Their conclusion? The project has been a mess since the beginning, and there are still no signs of improvement (although admittedly couched in far more diplomatic/technical language, to which we now turn).
--- End quote ---


http://www.theenergycollective.com/djwamsted/2406935/new-analysis-begs-question-vogtle-project-costly-complete