Shift rotating schedule

Started by zmayfieldwb37, May 31, 2021, 09:58

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

zmayfieldwb37

Does anyone know what the shift schedule is for limerick?


Also, If you work at a plant and wouldn't mind sharing what your schedule is that would be great.

m210

Different plant, but my plant's schedule rolls like this. D is 7a-7p, N is 7p-7a, T is 7a-3p (training). Night shifts begin the night before the day they're listed on the 'calendar'. Hopefully the formatting holds up

             M   T   W   R   F   S   S
Week 1: D   D   D   D   x   x   x
Week 2: N   N   N   N   x   x   x
Week 3:  x   x   x    x   D  D   D
Week 4:  x   x   x    x   N  N   N
Week 5:  x   T   T    T   T   x   x    then repeat to week 1

hamsamich

gotta love switching your sleep schedule 4 times every 35 days...I've done it and if I can help it will never do it again.  but some people love it!  if you can catch a good nap on nite shift...then ok.

m210

I don't mind it, really. Then again, I don't have kids yet either.

NukeWorker ™ is a registered trademark of NukeWorker.com ™, LLC © 1996-2025 All rights reserved.
All material on this Web Site, including text, photographs, graphics, code and/or software, are protected by international copyright/trademark laws and treaties. Unauthorized use is not permitted. You may not modify, copy, reproduce, republish, upload, post, transmit or distribute, in any manner, the material on this web site or any portion of it. Doing so will result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law.
Privacy Statement | Terms of Use | Code of Conduct | Spam Policy | Advertising Info | Contact Us | Forum Rules | Password Problem?