Shippingport Bridge Update: 9/24/09
The work on the Shippingport bridge continues in a very safe and productive manner. As our outage approaches, we can expect some changes to the current arrangement with Swank Construction and their schedule.
Swank Construction will be completing work on the three-span portion of the bridge by 10/9/09. This portion of the bridge spans over our entrance way into the plant. Swank will be moving their efforts northward towards the main bridge span on 10/9/09. The main span is considered the portion which spans over the river. Painting will begin under our section of the bridge on 9/28/09 and likewise finish on 10/9/09. The painters will be operating in an enclosed area under the bridge.
Swank will continue to work on the bridge with single lane operation during the outage with some additional arrangements. They include:
·Flagging of Traffic During Peak Hours - Swank will provide a certified flagman equipped with a cellular phone to manually operate the traffic lights during peak hours, Monday through Friday from 6:00 AM to 8:30 AM and 4:00 PM to 7:00 PM. Manually operating the traffic lights during the above mentioned days and times will ensure that no delays are experienced by FENCO employees, arriving to or departing from our facility.
·Emergency Services Access During Peak Hours - Swank’s Flagmen will be equipped with a cell phone for emergency communication with FENOC to ensure that emergency service vehicles have unimpeded travel through the work zone. Prior to any flagging operations we will provide FENCO with contact information. In the event of emergency FENOC will contact the emergency phone and instruct our flagmen on the direction of travel by the emergency vehicles, to ensure constant flow of traffic in the appropriate direction.
·Coordination/Communication with Borough Flagmen - An open line of communication will be available between Swank's Flagmen and the Borough Flagmen via 2-way radios to provide proper traffic flow in and out of the plant during peak hours.