Anybody know who has the HP contract for Waterford in October? I read that they are replacing both steam generators and the reactor head.....in 67 days. :o
DZ Atlantic, last I heard.
Quote from: 61nomad on Jul 29, 2012, 10:20
Anybody know who has the HP contract for Waterford in October? I read that they are replacing both steam generators and the reactor head.....in 67 days. :o
You meant to say "The schedule says they are replacing both steam generators and the reactor head.....in 67 days"....:)
Quote from: Dave Warren on Jul 31, 2012, 07:26
You meant to say "The schedule says they are replacing both steam generators and the reactor head.....in 67 days"....:)
Isn't October about 67 days away? The outage start date and the duration are both 67 days. Spooky. :D
How did that plan work out in reality?
Btw, I loved working at Waterford as a rent-a-tech.