NukeWorker Forum
News and Discussions => Nuke News => Topic started by: AP1000Ops on Nov 06, 2013, 09:56
-
Company press release:
"On Nov. 4, 2013, SCE&G completed placement of the nuclear island basemat for V.C. Summer Unit 3. This major milestone comes just seven months after SCE&G poured the first new construction nuclear concrete in the U.S. in three decades for its Unit 2 nuclear island. Crews worked through the night to complete the approximately 43-hour concrete placement on Nov. 4, 2013."