Title: Facility: DAVIS BESSE; ESSENTIAL BUSSES NOT ALIGNED TO POWER TRANSFORMERS DURING PLANT STARTUP (Event: 52247)
Post by: NukeWorkers News Team on Sep 20, 2016, 06:00
Facility: DAVIS BESSE; ESSENTIAL BUSSES NOT ALIGNED TO POWER TRANSFORMERS DURING PLANT STARTUP (Event: 52247)

Region: 3 State: OH
      Unit: [1] [ ] [ ]
      RX Type: [1] BandW-R-LP
      NRC Notified By: ANDY MILLER
      HQ OPS Officer: DANIEL MILLS
   
   
      Notification Date: 09/16/2016
      Notification Time: 23:35 [ET]
      Event Date: 09/16/2016
      Event Time: 16:57 [EDT]
      Last Update Date: 09/16/2016
   
 
 
   
      Emergency Class: NON EMERGENCY
      10 CFR Section:
      50.72(b)(3)(v)(A) - POT UNABLE TO SAFE SD
      50.72(b)(3)(v)(B) - POT RHR INOP
      50.72(b)(3)(v)(C) - POT UNCNTRL RAD REL
      50.72(b)(3)(v)(D) - ACCIDENT MITIGATION
   
   
      Person (Organization):
      STEVE ORTH (R3DO)
   
 



 
    Unit
    SCRAM Code
    RX CRIT
    Initial PWR
    Initial RX Mode
    Current PWR
    Current RX Mode
 
 
    1
    N
    N
    0
    Hot Shutdown
    0
    Hot Shutdown

Source: Facility: DAVIS BESSE; ESSENTIAL BUSSES NOT ALIGNED TO POWER TRANSFORMERS DURING PLANT STARTUP (Event: 52247) (http://www.nrc.gov/reading-rm/doc-collections/event-status/event/en.html#en52247)