H. B. Robinson was no hayride either. The S/Gs were cut out at the tubesheet and the new ones were manually welded into place from the inside. Bowls were layered with heat resistant blankets to protect the lead and lead blankets to reduce the exposure. Welders were in airline respirators and short staytimes. Did I mention that the S/G had to be heated while welding? Many happy times on nightshift there. Jumping the bowls for surveys and adjusting lead. I think that outage was only 7 or 8 months. How fast are they now?
[/quote]
I remember HB Robinson 1984; I was there for 2 years. I think the actual outage was 11 1/2 months “that was a money maker.”
I’m doing the ALARA thing at Comanche Peak right now, we are in outage day 23 and all 4 new S/G are set in place, RCS welding is in progress. We should shoot a flush RT on # 3 RSC cold leg tonight. At this pace we could come in under 60 days which would be a world record for a four loop Westinghouse. Yes, they are getting very fast!