Kairos Power began construction on the Hermes 2 demonstration facility in Oak Ridge, Tennessee, following a site groundbreaking on April 17. The project utilizes a fluoride salt-cooled reactor design to supply 50 MW of electricity to the Tennessee Valley Authority grid by 2030. Reactor modules will be fabricated in New Mexico before being shipped to the site for final assembly.

QuoteTerraPower and Kairos start building demonstration facilities Small Modular Reactor (SMR) developers Kairos Power and TerraPower both started building commercial-scale demonstration facilities in late April and said they expect to start producing power by 2030. Kairos Power broke ground on its Hermes 2 plant in Oak Ridge, Tennessee, on April 17...

The Tihange Nuclear Power Plant in Belgium. REUTERS/Johanna Geron

Kairos Power broke ground on its Hermes 2 plant in Oak Ridge, Tennessee, on April 17. Under an agreement with Google, the Hermes 2 fluoride salt-cooled, high-temperature reactor will produce 50 MW of clean electricity for the Tennessee Valley Authority (TVA) grid.

Kairos will fabricate Hermes 2 reactor equipment modules at its manufacturing campus in Albuquerque, New Mexico, and ship them to Oak Ridge for assembly.

Read the full article at reutersevents.com:
https://www.reutersevents.com/nuclear/terrapower-and-kairos-start-building-launch-pad-selects-microreactors-gas-plus-nuclear-planned