Susquehanna 1 completes Spring refueling outage in 43 days

Started by News Wire, Yesterday at 04:54

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

News Wire


Susquehanna 1 finished its refueling outage in 43 days, completing the work three days ahead of the 46-day schedule. This duration is 0.2 days below the average of the unit's 14 tracked refuels. The unit entered this spring outage following an unscheduled-outage-free streak of 127 days.

43 days outage · 3 days ahead of schedule · 1,247 MW back online

Susquehanna 1 resumed power production on May 4, 2026 after a 43-day Spring 2026 refueling outage that began Mar 23, 2026.

The published schedule had it at 46 days (Mar 23, 2026 to May 8, 2026), so the actual ran 3 days shorter than planned.

The 43-day outage removed roughly 1.18 million MWh from the grid, worth approximately $47 million at recent wholesale prices, equivalent to a year's electricity for about 110,000 homes.

Across the U.S. fleet of 94 commercial reactors, today's combined capacity factor is 91.3% (5 currently in refueling), above the 87.0% baseline for this month over the past five years. At the same site, Susquehanna 2 is running at full power. Palo Verde 2, Beaver Valley 2, Braidwood 2, and Seabrook 1 also completed refueling outages within the past week.

Susquehanna 1 is a 1,247-MW General Electric BWR/4 operated by TalenEnergy Susquehanna (commercial operation since 1983). At full power, it supplies enough electricity for roughly 998,000 homes. The utility operates 1 other U.S. nuclear unit. Its operating license runs through 2042 (renewed in 2009). The unit ran at a 96.7% capacity factor in 2025, among the unit's strongest cycles.

View Susquehanna 1's ratings, history, predictions, and current status on NukeWorker.

Want the full picture? Subscribe to the NukeWorker outage schedule for every current and upcoming U.S. nuclear outage: refueling, forced, and the 18-month rolling forecast.

Sources: NRC Daily Reactor Power Status reports, utility-published outage schedules, and NukeWorker's predictive model.