South Texas 1 completes Spring refuel in 33 days, caps 497-day B2B run

Started by News Wire, Yesterday at 04:58

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

News Wire


South Texas 1 completed its refueling outage in 33 days, which was one day longer than the planned 32-day schedule. This duration is 13.2 days below the average of the unit's 17 prior refuels. The outage concluded following a 747-day unscheduled-outage-free streak for the 1,280-MW Westinghouse 4-loop PWR.

33 days outage · 1 day past schedule · ninth B2B run complete · 1,280 MW back online

South Texas 1 resumed power production on Apr 22, 2026 after a 33-day Spring 2026 refueling outage that began Mar 21, 2026.

The published schedule had it at 32 days (Mar 20, 2026 to Apr 21, 2026), so the actual ran 1 day longer than planned.

The outage ran about 13 days shorter than the unit's 17-cycle average of 46.2 days. It also capped a 497-day breaker-to-breaker run (over the 454-day threshold for an 18-month cycle), the unit's ninth qualified B2B run. Going into the refueling, the unit had run for more than 2 years without an unscheduled outage. NukeWorker's predictive model scores 95% on duration accuracy for this unit.

The 33-day outage removed roughly 933,000 MWh from the grid, worth approximately $37 million at recent wholesale prices, equivalent to a year's electricity for about 86,000 homes.

Across the U.S. fleet of 94 commercial reactors, today's combined capacity factor is 91.3% (5 currently in refueling), above the 87.0% baseline for this month over the past five years. At the same site, South Texas 2 is running at full power. Quad Cities 2, Ginna, and McGuire 2 also completed refueling outages within the past week.

South Texas 1 is a 1,280-MW Westinghouse 4-loop PWR operated by STP Nuclear Operating (commercial operation since 1988). At full power, it supplies enough electricity for roughly 1 million homes. The utility operates 1 other U.S. nuclear unit. Its operating license runs through 2047 (renewed in 2017). The unit ran at a 100.0% capacity factor in 2025, among the unit's strongest cycles.

View South Texas 1's ratings, history, predictions, and current status on NukeWorker.

Want the full picture? Subscribe to the NukeWorker outage schedule for every current and upcoming U.S. nuclear outage: refueling, forced, and the 18-month rolling forecast.

Sources: NRC Daily Reactor Power Status reports, utility-published outage schedules, and NukeWorker's predictive model.