Prediction Explanation: Cooper

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

FeatureValueImpact (days)
Cycle Length (days) 728.0 -66.57 days
Containment Type BWR-MARK 1 +9.89 days
Previous Outage Duration 42.0 +6.49 days
Reactor Type (NSSS) GE 4 +5.66 days
Fleet Outages This Year N/A -3.84 days
Age at Outage (years) 52.2 +3.75 days
3-Outage Rolling Avg Duration 26.0 +2.48 days
Fleet Density 0.0 +2.24 days
Avg Outages Between Major Maint. 26.1 +2.11 days
Net Capacity (MWe) 770.0 +2.03 days