Prediction Explanation: Diablo Canyon 2

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

FeatureValueImpact (days)
Cycle Length (days) 546.0 -30.27 days
Reactor Type (NSSS) WEST 4LP -5.7 days
Containment Type PWR-DRYAMB -5.67 days
Fleet Outages This Year N/A -2.17 days
Days Since Fleet Prev Outage N/A -1.67 days
State CA -1.55 days
Fleet Density 0.0 +1.42 days
Previous Outage Duration 42.0 +1.31 days
Net Capacity (MWe) 1118.0 -1.25 days
Forced Outage Days in Cycle 0.0 +0.99 days

Start Date — Global Importance

Duration — Global Importance