NukeWorker Menu

Prediction Explanation: Ginna

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

FeatureValueImpact (days)
Cycle Length (days) 553.0 -36.65 days
Containment Type PWR-DRYAMB -7.93 days
Net Capacity (MWe) 581.0 -3.02 days
Reactor Type (NSSS) WEST 2LP -2.93 days
Previous Outage Duration 15.0 -2.22 days
Fleet Density 0.0 +2.15 days
Licensed Capacity (MWt) 1775.0 -2.06 days
3-Outage Rolling Avg Duration 13.0 +1.93 days
Fleet Outages This Year 6.0 -1.75 days
Units at Site 1.0 +1.72 days

Start Date — Global Importance

Duration — Global Importance