FeatureValueImpact (days)
Cycle Length (days) 735.0 -71.22 days
Containment Type BWR-MARK 1 +11.71 days
Reactor Type (NSSS) GE 2 +6.85 days
Age at Outage (years) 57.3 +3.19 days
Avg Outages Between Major Maint. 27.0 +3.16 days
Net Capacity (MWe) 621.0 +2.94 days
Forced Outage Days in Cycle 0.0 +2.66 days
3-Outage Rolling Avg Duration 24.3 +2.48 days
Fleet Outages This Year 6.0 -2.2 days
Licensed Capacity (MWt) 1850.0 -1.57 days

Start Date — Global Importance

Duration — Global Importance