Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

FeatureValueImpact (days)
Cycle Length (days) 731.0 -82.62 days
Reactor Type (NSSS) B&W LLP +11.52 days
Containment Type PWR-DRYAMB -5.72 days
Licensed Capacity (MWt) 2610.0 -4.65 days
Age at Outage (years) 53.1 +3.87 days
Net Capacity (MWe) 848.0 +2.99 days
State SC +2.95 days
Avg Outages Between Major Maint. 22.1 +2.92 days
Forced Outage Days in Cycle 0.0 +2.32 days
Fleet Density 0.0 +2.11 days

Start Date — Global Importance

Duration — Global Importance