Prediction Explanation: Palo Verde 3
Feature importance and per-unit prediction explanations for the model.
Per-Unit Prediction Explanation
Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.
| Feature | Value | Impact (days) |
| Cycle Length (days) |
546.0 |
-34.09 days
|
| Containment Type |
PWR-DRYAMB |
-5.01 days
|
| Reactor Type (NSSS) |
COMB CE80 |
+2.77 days
|
| State |
AZ |
-2.58 days
|
| Fleet Outages This Year |
1.0 |
-2.04 days
|
| Forced Outage Days in Cycle |
0.0 |
+1.78 days
|
| Outage Number (experience) |
20.0 |
-1.2 days
|
| Owner |
Arizona Public Service |
-1.11 days
|
| Days Since Fleet Prev Outage |
N/A |
-1.04 days
|
| Avg Outages Between Major Maint. |
18.5 |
+1.02 days
|
Start Date — Global Importance
Duration — Global Importance