Prediction Explanation: Peach Bottom 3

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

FeatureValueImpact (days)
Cycle Length (days) 728.0 -63.38 days
Containment Type BWR-MARK 1 +11 days
Reactor Type (NSSS) GE 4 +6.37 days
3-Outage Rolling Avg Duration 14.7 +3.29 days
Forced Outage Days in Cycle 0.0 +2.45 days
Fleet Density 0.0 +1.74 days
Age at Outage (years) 52.8 +1.7 days
State PA +1.34 days
Day of Week 1.0 -1.32 days
Outage Number (experience) 14.0 -0.95 days

Start Date — Global Importance

Duration — Global Importance