Prediction Explanation: Point Beach 2

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

FeatureValueImpact (days)
Cycle Length (days) 518.0 -10.2 days
Containment Type PWR-DRYAMB -6.56 days
Reactor Type (NSSS) WEST 2LP -3.83 days
Forced Outage Days in Cycle 0.0 +2.35 days
Fleet Outages This Year 3.0 -2.21 days
Previous Outage Duration 19.0 -1.86 days
Days Since Fleet Prev Outage 38.0 +1.75 days
Net Capacity (MWe) 603.0 -1.66 days
Avg Outages Between Major Maint. 15.1 +1.57 days
Day of Week 6.0 +1.32 days

Start Date — Global Importance

Duration — Global Importance