Prediction Explanation: Saint Lucie 1

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

FeatureValueImpact (days)
Cycle Length (days) 560.0 -38.93 days
Containment Type PWR-DRYAMB -10.58 days
Reactor Type (NSSS) COMB CE +3.32 days
State FL -2.52 days
Age at Outage (years) 50.2 +1.99 days
Fleet Outages This Year 3.0 -1.59 days
Owner NextEra Energy -1.58 days
Avg Outages Between Major Maint. 14.4 +1.54 days
Log Outage Number 2.0 +1.35 days
Fleet Density 1.0 -1.21 days

Start Date — Global Importance

Duration — Global Importance