Prediction Explanation: Saint Lucie 2
Feature importance and per-unit prediction explanations for the model.
Per-Unit Prediction Explanation
Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.
| Feature | Value | Impact (days) |
| Cycle Length (days) |
560.0 |
-38.37 days
|
| Containment Type |
PWR-DRYAMB |
-11.29 days
|
| Forced Outage Days in Cycle |
21.0 |
-3.99 days
|
| Forced Outage Count in Cycle |
4.0 |
+3.38 days
|
| Reactor Type (NSSS) |
COMB CE |
+3.14 days
|
| Log Outage Number |
2.0 |
+2.24 days
|
| Avg Outages Between Major Maint. |
13.7 |
+1.96 days
|
| State |
FL |
-1.89 days
|
| Age at Outage (years) |
44.1 |
+1.39 days
|
| Owner |
NextEra Energy |
-1.36 days
|
Start Date — Global Importance
Duration — Global Importance
Page created in 0.042 seconds with 0 queries.