Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

FeatureValueImpact (days)
Cycle Length (days) 560.0 -38.37 days
Containment Type PWR-DRYAMB -11.29 days
Forced Outage Days in Cycle 21.0 -3.99 days
Forced Outage Count in Cycle 4.0 +3.38 days
Reactor Type (NSSS) COMB CE +3.14 days
Log Outage Number 2.0 +2.24 days
Avg Outages Between Major Maint. 13.7 +1.96 days
State FL -1.89 days
Age at Outage (years) 44.1 +1.39 days
Owner NextEra Energy -1.36 days

Start Date — Global Importance

Duration — Global Importance