Projection Explanation: Vogtle 2
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Containment Type |
PWR-DRYAMB |
-9.72 days |
| Cycle Length (days) |
556.0 |
+5.35 days |
| Licensed Capacity (MWt) |
3626.0 |
-4.63 days |
| Reactor Type (NSSS) |
WEST 4LP |
-3.19 days |
| Net Capacity (MWe) |
1152.0 |
-1.87 days |
| Age at Outage (years) |
38.8 |
+1.78 days |
| Balancing Authority |
SOCO |
-1.66 days |
| Units at Site |
4.0 |
-1.27 days |
| cycle_interval_std |
12.6 |
-0.91 days |
| Month |
3.0 |
+0.84 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?