Connecticut Yankee (Haddam Neck)
The plant was shut down on July 22, 1996. The fuel was removed from the reactor vessel on November 5, 1996. The owner submitted certification of permanent cessation of operations on December 5, 1996. The post-shutdown decommissioning activities report (PSDAR) was submitted August 22, 1997. The PSDAR public meeting was held on October 27, 1997. The owner submitted a License Termination Plan (LTP) on July 7, 2000. A public meeting on the LTP was held October 17, 2000. NRC completed its review of the LTP on November 25, 2002. The owner is using the DECON option.