NukeWorker Menu

Prediction Explanation: Hatch 2

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

FeatureValueImpact (days)
Cycle Length (days) 46.0 +562.19 days
Containment Type BWR-MARK 1 +37.12 days
Reactor Type (NSSS) GE 4 +14.71 days
Age at Outage (years) 47.4 +4.86 days
Days Since Fleet Prev Outage N/A -4.63 days
Forced Outage Days in Cycle 0.0 +4.55 days
Fleet Outages This Year 1.0 -4.3 days
Month 2.0 -3.59 days
Avg Outages Between Major Maint. 17.2 +3.03 days
Owner Southern Nuclear +2.88 days

Start Date — Global Importance

Duration — Global Importance