Prediction Explanation: Hatch 2
Feature importance and per-unit prediction explanations for the model.
Per-Unit Prediction Explanation
Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.
| Feature | Value | Impact (days) |
| Cycle Length (days) |
46.0 |
+562.19 days
|
| Containment Type |
BWR-MARK 1 |
+37.12 days
|
| Reactor Type (NSSS) |
GE 4 |
+14.71 days
|
| Age at Outage (years) |
47.4 |
+4.86 days
|
| Days Since Fleet Prev Outage |
N/A |
-4.63 days
|
| Forced Outage Days in Cycle |
0.0 |
+4.55 days
|
| Fleet Outages This Year |
1.0 |
-4.3 days
|
| Month |
2.0 |
-3.59 days
|
| Avg Outages Between Major Maint. |
17.2 |
+3.03 days
|
| Owner |
Southern Nuclear |
+2.88 days
|
Start Date — Global Importance
Duration — Global Importance
Page created in 0.011 seconds with 0 queries.