Projection Explanation: Browns Ferry 3

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 735.0 -53.56 days
Containment Type BWR-MARK 1 +25.64 days
State AL -5.11 days
Prior Cycle Length (months) 24.2 +4.89 days
Years to License Expiration 28.4 +4.59 days
unit_pct_in_predicted_month 0.6 +3.72 days
Reactor Type (NSSS) GE +3.56 days
Forced Outage Days in Cycle 33.0 -2.68 days
unit_pct_in_spring_fall 0.4 +1.79 days
Balancing Authority TVA +1.6 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?