Prediction Explanation: Vogtle 1
Feature importance and per-unit prediction explanations for the model.
Per-Unit Prediction Explanation
Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.
| Feature | Value | Impact (days) |
| Cycle Length (days) |
532.0 |
-19.04 days
|
| Reactor Type (NSSS) |
WEST 4LP |
-5.98 days
|
| Containment Type |
PWR-DRYAMB |
-5.17 days
|
| Fleet Outages This Year |
1.0 |
-1.84 days
|
| Days Since Fleet Prev Outage |
N/A |
-1.76 days
|
| Fleet Density |
0.0 |
+1.24 days
|
| Net Capacity (MWe) |
1150.0 |
-1.05 days
|
| Owner |
Southern Nuclear |
+0.92 days
|
| Forced Outage Days in Cycle |
0.0 |
+0.89 days
|
| Units at Site |
4.0 |
+0.78 days
|
Start Date — Global Importance
Duration — Global Importance