Every power reactor at this site as listed in the IAEA Power Reactor Information System (PRIS): reactor type and model, net electrical capacity, grid connection and commercial operation dates, and current status.
5 units: 4 operational, 1 permanent shutdown. Net capacity in service: 3,580 MWe.
Unit Type Model Net MWe Construction Grid Commercial Op Shutdown Status
Bugey 1 GCR UNGG 540 1965-12-01 1972-04-15 1972-07-01 1994-05-27 Permanent Shutdown
Bugey 2 PWR CP0 910 1972-11-01 1978-05-10 1979-03-01 Operational
Bugey 3 PWR CP0 910 1973-09-01 1978-09-21 1979-03-01 Operational
Bugey 4 PWR CP0 880 1974-06-01 1979-03-08 1979-07-01 Operational
Bugey 5 PWR CP0 880 1974-07-01 1979-07-31 1980-01-03 Operational
Capacity, milestones and suppliers
Unit Design MWe Gross MWe Thermal MWt First Criticality Reactor Supplier Turbine Supplier Notes
Bugey 1 540 555 1,954 1972-03-21 FRAMATOME ALSTOM
Bugey 2 920 945 2,785 1978-04-20 FRAMATOME FRAMATOME
Bugey 3 920 945 2,785 1978-08-31 FRAMATOME FRAMATOME
Bugey 4 900 917 2,785 1979-02-17 FRAMATOME FRAMATOME
Bugey 5 900 917 2,785 1979-07-15 FRAMATOME FRAMATOME
Lifetime performance, through 2025
Unit Electricity Supplied Load Factor Energy Availability Operating Factor
Bugey 1 55.3 TWh 53.4% 66.6% 70.3%
Bugey 2 258.0 TWh 68.4% 72.0% 73.8%
Bugey 3 248.5 TWh 66.1% 70.1% 71.3%
Bugey 4 251.3 TWh 70.1% 74.2% 75.8%
Bugey 5 244.1 TWh 68.0% 72.3% 74.0%
Operator: ÉLECTRICITÉ DE FRANCE
Owner: ÉLECTRICITÉ DE FRANCE
Source: IAEA Power Reactor Information System (PRIS), as of 2026-11-02.

Working Here

Per Diem Rates FY 2026

?
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from the U.S. State Department foreign per diem tables for FY 2026.
$220
Lodging/Night
$132
M&IE/Day
$352
Total/Day
France: rate for locations the State Department does not list separately
U.S. Department of State foreign per diem, for U.S. government and contractor travel.

Location & Contact

?
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Address:
Saint-Vulbas, Auvergne-Rhône-Alpes, France
Get Directions

Plant Facts

About This Site

?
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: Wikipedia: Bugey Nuclear Power Plant.

Bugey is a nuclear power site in the commune of Saint-Vulbas, in the Ain department of Auvergne-Rhône-Alpes, on the bank of the Rhône about 35 km upstream of Lyon. It has five reactor units.

Read more

Site work began in 1964. Bugey 1, a gas-cooled, graphite-moderated (UNGG) unit, began construction in December 1965, was connected to the grid in April 1972, and was permanently shut down on 27 May 1994. Bugey 2 through 5 are pressurized water reactors of the CP0 design, started between 1972 and 1974 and first connected to the grid between May 1978 and July 1979. During the heat wave of July 2003, waste heat was discharged directly into the Rhône on two occasions.