Dungeness
Romney Marsh, Kent
Reactor Data
Reactor Units
| Unit | Type | Model | Net MWe | Construction | Grid | Commercial Op | Shutdown | Status |
|---|---|---|---|---|---|---|---|---|
| Dungeness A-1 | GCR | MAGNOX | 225 | 1960-07-01 | 1965-09-21 | 1965-10-28 | 2006-12-31 | Permanent Shutdown |
| Dungeness A-2 | GCR | MAGNOX | 225 | 1960-07-01 | 1965-11-01 | 1965-12-30 | 2006-12-31 | Permanent Shutdown |
| Dungeness B-1 | GCR | AGR | 545 | 1965-10-01 | 1983-04-03 | 1985-04-01 | 2021-06-07 | Permanent Shutdown |
| Dungeness B-2 | GCR | AGR | 545 | 1965-10-01 | 1985-12-29 | 1989-04-01 | 2021-06-07 | Permanent Shutdown |
| Unit | Design MWe | Gross MWe | Thermal MWt | First Criticality | Reactor Supplier | Turbine Supplier | Notes |
|---|---|---|---|---|---|---|---|
| Dungeness A-1 | 275 | 230 | 840 | 1965-06-01 | THE NUCLEAR POWER GROUP, LTD. | C.A.PARSONS | |
| Dungeness A-2 | 275 | 230 | 840 | 1965-09-01 | THE NUCLEAR POWER GROUP, LTD. | C.A.PARSONS | |
| Dungeness B-1 | 607 | 615 | 1,500 | 1982-12-23 | ATOMIC POWER CONSTRUCTION, LTD. | C.A.PARSONS | |
| Dungeness B-2 | 607 | 615 | 1,500 | 1985-12-04 | ATOMIC POWER CONSTRUCTION, LTD. | C.A.PARSONS |
| Unit | Electricity Supplied | Load Factor | Energy Availability | Operating Factor |
|---|---|---|---|---|
| Dungeness A-1 | 59.2 TWh | 74.0% | 74.3% | 86.5% |
| Dungeness A-2 | 60.7 TWh | 74.9% | 75.1% | 86.9% |
| Dungeness B-1 | 94.6 TWh | 42.0% | 42.9% | 51.3% |
| Dungeness B-2 | 99.6 TWh | 47.9% | 48.1% | 55.0% |
Working Here
Per Diem Rates FY 2026
Photos
Facility Map
50.9133, 0.963974
Location & Contact
Plant Facts
About This Site
Dungeness is a nuclear power station site on the Dungeness headland on Romney Marsh in Kent, southern England, on a large area of shingle surrounded by a Site of Special Scientific Interest. It has two stations, Dungeness A and Dungeness B.
Read more
Dungeness A had two Magnox reactors, built by The Nuclear Power Group, and was connected to the grid in 1965. Generation ceased on 31 December 2006, and defuelling was completed in June 2012. Dungeness B has two advanced gas-cooled reactors, with the construction contract awarded in August 1965. Reactor 1 first generated power on 3 April 1983, about 13 years behind schedule, and reactor 2 began operation in 1985. Both were permanently shut down on 7 June 2021.