Helo in 2MW would be ridiculously easy.
The EDG is on a skid, made up of components. It would take me 2 hours to disassembly the skid, and 2-3 hours to reassemble. I would disassemble the skid even if I had a russian Miv 26 chopper so that I could easily move the power in position where I needed it.
The plant seemed to put too much into the running the cable. It seems to be a failure so far. The pumps are still being run by diesel generators (and where fire truck pumpers before that). Running those cables restricts where you tap into and exposed people to high rad. It might have been ok for a backup plan, but as the only plan it is a failure. Took too long. You need power before you can even trouble shoot the system. The fight doesn't even start until you have power. A break down in basic critical problem solving. Should have set the time constraint as 24 hours, that would have taken "pull the cable 2500 ft" off the table.
Getting all the power I need is the easy part of the problem. I figure 12 hours to located, stage, and line up resources. 12 hour to get the first 2MW for each plant available. 24 total. Then in a day or two I would not be power limited. The hard part would then start-trying to cobble together what works, what don't, get parts, fabricate, install, test. Of course, they get power in there within 24 hours they don't have high rad and explosion damage. They made a workable problem a complete disaster by failure to act. +5billion dollar clean up Fission products in the ocean. And 5GW off the grid that needs to be replaced.
I would rate getting power complexity as 1 star out of 5.
One 2000kw detroit diesel gen, skid mounted:
http://www.dieselgeneratorsmiami.com/generalpower/650-kw-to-2000-kw-diesel-generators/218/2000-kw-diesel-generator-2500-kva-60-hz-three-phase-sdmo-x2000uii-detroit-mtu-diesel-generator-open-skid-mounted-version.htmlThe diesel is 6 tons. (I can disassemble this to the crank/block if needed)
The generator is 4 tons. ( I can further separate the stator - rotor-if needed.)
The skid is 2-3 tons
The Exciter/controls/cooler is 2-3 tons.
Total is 15 tons.
Each medium lift chinook chopper is rated oh..10 tons. My weight limit is the diesel. Barely over 50% capacity.
Anyway, its better then TEPCO's "cops with water canon" plan that got rolled out after 8 days.