Help | Contact Us
NukeWorker.com
NukeWorker Menu Georgia Power will move forward with Vogtle 3 & 4 project honeypot

Author Topic: Georgia Power will move forward with Vogtle 3 & 4 project  (Read 1788 times)

0 Members and 1 Guest are viewing this topic.

Offline Marlin

  • Forum Staff
  • *
  • Posts: 18978
  • Karma: 5147
  • Gender: Male
  • Stop Global Whining!!!
« Last Edit: Dec 21, 2017, 10:50 by Marlin »

Offline SloGlo

  • meter reader
  • Very Heavy User
  • *****
  • Posts: 5834
  • Karma: 2646
  • Gender: Male
  • trust me, i'm an hp
Re: Georgia Power will move forward with Vogtle 3 & 4 project
« Reply #1 on: Dec 21, 2017, 11:30 »
grate knews! is Bechtel the construction company witch will complete?
« Last Edit: Dec 21, 2017, 11:31 by SloGlo »
quando omni flunkus moritati

dubble eye, dubble yew, dubble aye!

dew the best ya kin, wit watt ya have, ware yinze are!

Offline Ksheed

  • Very Lite User
  • *
  • Posts: 4
  • Karma: 0
  • Gender: Male
  • Tell Recruiters to use NukeWorker.com
Re: Georgia Power will move forward with Vogtle 3 & 4 project
« Reply #2 on: Dec 21, 2017, 12:05 »
grate knews! is Bechtel the construction company witch will complete?


Sounds like it:


Quote
Construction has continued uninterrupted at the Vogtle site following Westinghouse's bankruptcy in March with all Vogtle co-owners working together to maintain the project's momentum. Southern Nuclear, the nuclear operating subsidiary which operates the existing units in Georgia, is now the project manager at the site with global construction firm Bechtel managing daily construction efforts.  Progress is steady and evident, illustrated by multiple recent achievements such as the placement of new shield building panels for both units, placement of the 52-ton CA02 module for Unit 4 and the installation of the first steam generator.

Offline Marlin

  • Forum Staff
  • *
  • Posts: 18978
  • Karma: 5147
  • Gender: Male
  • Stop Global Whining!!!
Re: Georgia Power will move forward with Vogtle 3 & 4 project
« Reply #3 on: Dec 21, 2017, 12:38 »

grate knews! is Bechtel the construction company witch will complete?

This article seems to confirm Bechtel is continuing as well.

Georgia PSC approves Vogtle completion

Construction has continued uninterrupted at Vogtle following Westinghouse's bankruptcy, with Southern Nuclear taking over as project manager at the site and Bechtel managing construction. "Progress is steady and evident, illustrated by multiple recent achievements such as the placement of new shield building panels for both units, placement of the 52-ton CA02 module for Unit 4 and the installation of the first steam generator," Georgia Power said.

http://www.world-nuclear-news.org/NN-Georgia-PSC-approves-Vogtle-completion-2112177.html

 


NukeWorker ™ is a registered trademark of NukeWorker.com ™, LLC © 1996-2025 All rights reserved.
All material on this Web Site, including text, photographs, graphics, code and/or software, are protected by international copyright/trademark laws and treaties. Unauthorized use is not permitted. You may not modify, copy, reproduce, republish, upload, post, transmit or distribute, in any manner, the material on this web site or any portion of it. Doing so will result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law.
Privacy Statement | Terms of Use | Code of Conduct | Spam Policy | Advertising Info | Contact Us | Forum Rules | Password Problem?