Palisades enters final stage of work before restart

Started by Marlin, Jul 03, 2026, 12:52

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

nrcPalisadesholtec international

Marlin


Core Content

The Palisades turbine-generator on turning gear (Image: Holtec)

Holtec International has transitioned the Palisades site from large-scale construction projects to routine maintenance, testing, and operational readiness activities. Recent milestones include the installation of a new fuel handling machine and the placement of the turbine-generator on turning gear. The plant is now preparing for final regulatory verification and startup procedures after ceasing operations in 2022.

QuoteHoltec International announced that over the past several weeks, the Palisades restart project reached a "watershed moment" as the last of the major projects were successfully closed out and the site transitioned from large-scale activities to the remaining routine maintenance, testing, inspection, and operational readiness work required before...

Among the final accomplishments in this 'project phase' of restart was placement of the plant's turbine-generator on turning gear following extensive inspections, maintenance, testing, and refurbishment activities. Holtec said another major achievement was installation and testing of a new state-of-the-art fuel handling machine, completing the upgraded fuel handling system.

Read the full article at World Nuclear News:
https://world-nuclear-news.org/articles/palisades-enters-final-stage-of-work-before-restart

fiveeleven

Odd there is no mention of forecasted startup date. 5K work orders could be awhile.