Projection Explanation: Beaver Valley 1

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 547.0 +13.08 days
Containment Type PWR-DRYAMB -9.13 days
Reactor Type (NSSS) WEST 3LP -4.34 days
Licensed Capacity (MWt) 2900.0 -1.37 days
Units at Site 2.0 -1.35 days
State PA +1.32 days
Net Capacity (MWe) 907.0 -1.04 days
Outage Number (experience) 18.0 -1 days
Balancing Authority PJM -0.6 days
Years to License Expiration 8.8 -0.51 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?