Projection Explanation: Browns Ferry 1

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 742.0 -54.54 days
Containment Type BWR-MARK 1 +30.6 days
Reactor Type (NSSS) GE 4 +2.69 days
Prior Cycle Length (months) 24.4 +2.46 days
unit_modal_month 10.0 -2.12 days
Units at Site 3.0 -1.97 days
unit_pct_in_predicted_month 0.1 -1.72 days
NRC Region 2.0 +0.99 days
Forced Outage Days in Cycle 8.0 +0.91 days
Avg Coastdown Days (this unit) 27.5 +0.89 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?