Prediction Explanation: Clinton
Feature importance and per-unit prediction explanations for the model.
Per-Unit Prediction Explanation
Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.
| Feature | Value | Impact (days) |
| Cycle Length (days) |
728.0 |
-62.45 days
|
| Containment Type |
BWR-MARK 3 |
+14.37 days
|
| Reactor Type (NSSS) |
GE 6 |
+6.84 days
|
| Forced Outage Days in Cycle |
0.0 |
+2.6 days
|
| Days Since Fleet Prev Outage |
N/A |
-2.58 days
|
| Licensed Capacity (MWt) |
3473.0 |
+2.32 days
|
| Avg Outages Between Major Maint. |
27.3 |
+1.81 days
|
| Fleet Outages This Year |
6.0 |
-1.38 days
|
| Units at Site |
1.0 |
+1.3 days
|
| Owner |
Constellation Energy |
-1.2 days
|
Start Date — Global Importance
Duration — Global Importance