Projection Explanation: Columbia Generating Station
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Containment Type |
BWR-MARK 2 |
+26.44 days |
| Cycle Length (days) |
707.0 |
-22.6 days |
| Units at Site |
1.0 |
+5.49 days |
| Avg Outages Between Major Maint. |
4.3 |
-4.9 days |
| State |
WA |
+4.17 days |
| Reactor Type (NSSS) |
GE 5 |
+3.13 days |
| NRC Region |
4.0 |
-2.19 days |
| Outage Number (experience) |
14.0 |
-2.08 days |
| Fleet Outages This Year |
N/A |
+1.46 days |
| Age at Outage (years) |
42.3 |
+1.44 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?