Projection Explanation: LaSalle 1

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 721.0 -35.27 days
Containment Type BWR-MARK 2 +24.65 days
Prior Cycle Length (months) 23.7 +5.09 days
Reactor Type (NSSS) GE 5 +3.49 days
unit_pct_in_predicted_month 0.8 +3 days
unit_pct_in_spring_fall 0.0 +1.67 days
Units at Site 2.0 -1.54 days
unit_pct_in_winter 1.0 +1.54 days
Years to License Expiration 14.2 -1.17 days
Season winter -0.84 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?