FeatureValueImpact (days)
Cycle Length (days) 728.0 -32.78 days
Containment Type BWR-MARK 2 +21.07 days
Reactor Type (NSSS) GE 5 +3.36 days
Prior Cycle Length (months) 23.9 +1.68 days
unit_pct_in_winter 0.9 +1.44 days
Month 2.0 -1.31 days
Units at Site 2.0 -1.28 days
Age at Outage (years) 42.3 +0.92 days
Outage Number (experience) 15.0 -0.82 days
Fleet Outages This Year 10.0 +0.72 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?