Projection Explanation: North Anna 2

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Containment Type PWR-DRYSUB -12.77 days
Years to License Expiration 32.5 +11.56 days
Cycle Length (days) 553.0 +10.9 days
Reactor Type (NSSS) WEST 3LP -3.9 days
State VA +1.43 days
Units at Site 2.0 -1.41 days
Licensed Capacity (MWt) 2940.0 -1 days
Outage Number (experience) 19.0 -0.93 days
Net Capacity (MWe) 944.0 -0.8 days
Balancing Authority PJM -0.7 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?