| Reactor | Type | Thermal Power | First Criticality | Shutdown | Status | Used For |
|---|---|---|---|---|---|---|
| HTR Hanford Test Reactor | Graphite | 30 Wt | 1945-02-01 | Decommissioned | materials testing | |
| PCTR Physical Constants Test Reactor | Graphite | 10 Wt | 1955-10-01 | Decommissioned | materials testing, nuclear data | |
| TTR-2 Thermal Test Reactor | Graphite Pile | 1 kWt | 1958-01-01 | Decommissioned | activation analysis, nuclear data | |
| Plutonium Recycle Test Reactor | Heavy Water | 85 MWt | 1960-01-01 | Decommissioned | materials testing | |
| PNNL-CML Critical Mass Lab | Homog (l) | 1961-01-01 | Decommissioned | |||
| PRCF Plutonium Recycle Critical | Crit Assembly | 1 kWt | 1962-01-01 | Decommissioned | neutron radiography, materials testing, nuclear data | |
| HTLTR High Temp Lattice Test Reactor | Graphite | 2 kWt | 1967-11-01 | Decommissioned | nuclear data | |
| NRF, Neutron Rad Facility | Triga Mark I | 1 MWt | 1977-03-01 | Under decommissioning | neutron radiography, materials testing | |
| FFTF, Fast Flux Test | Fast, Na Cooled | 4 MWt | 1980-02-09 | Under decommissioning | isotope production, materials testing |
Fuel Cycle Facilities
| Facility | Type | Scale | Design Capacity | Operated | Status | Operator |
|---|---|---|---|---|---|---|
| Hanford - K Basins | AFR Wet Spent Fuel Storage (Pool) | Laboratory | 2100 t HM | 1950– | In Operation | |
| Hanford T Plant Complex | Spent Fuel Reprocessing - aqueous route | Commercial | 0 t HM/year | 1944–1956 | Decommissioning | |
| Hanford - Plutonium Finishing Plant | MOX fuel fabrication (Mox Powder, Pellet, Pin, FA) | Laboratory | 0 t HM/year | 1949–1989 | Shutdown | |
| Hanford Redox Facility | Spent Fuel Reprocessing - aqueous route | Pilot plant | 0 t HM/year | 1949–1956 | Decommissioning | |
| Hanford | Conversion to UO3 | Laboratory | 0 t HM/year | 1956–1972 | Shutdown | |
| Hanford - B Plant | Spent Fuel Reprocessing - aqueous route | Laboratory | 2400 t HM/year | 1956–1989 | Decommissioning | |
| Hanford | Fuel Fabrication (U Pellet, Pin, FA) | Laboratory | 0 t HM/year | 1961–1989 | Shutdown | |
| Hanford - Canister Storage Building | AFR Dry Spent Fuel Storage | Laboratory | 2300 t HM | 2003– | Under Construction | |
| Fuels and Materials Examination Fac. (FMEF) | MOX fuel fabrication (Mox Powder, Pellet, Pin, FA) | Laboratory | 0 t HM/year | Stand By |
Working Here
Jobs at Hanford 2 active
More Jobs in WA 11 active
Per Diem Rates FY 2027
Unemployment Benefits WA
Photos
Facility Map
46.5527, -119.528
Location & Contact
NukeWorker Member Ratings 44 votes
Plant Facts
About This Site
The Hanford Site is a former plutonium production complex covering about 586 square miles of Benton County, Washington, near Richland. The Columbia River forms its northern and eastern boundary for roughly 50 miles.
Read more
General Leslie Groves approved the site on January 16, 1943, for the Manhattan Project, and it operated as the Hanford Engineer Works. B Reactor was completed on September 13, 1944, and produced its first plutonium on November 6, 1944. Plutonium from Hanford went into the Trinity test device in 1945 and the bomb dropped on Nagasaki on August 9, 1945. Cold War expansion brought the total to nine production reactors and five reprocessing plants. B Reactor was shut down on February 12, 1968.