The plant was shut down in November 1992. The DECON decommissioning plan was approved in April 1996. The plant is currently undergoing dismantlement. The steam generators and reactor vessel have been shipped to Hanford LLW site. The owner was granted a site-specific license for an onsite ISFSI in March 1999. The owner submitted a License Termination Plan (LTP) in August of 1999 and a public meeting was held in St. Helens, Oregon on December 7, 1999. A license amendment was issued in February 2001, approving the LTP. The owner has completed transferring fuel from the spent fuel pool into transportable dry storage systems at an on-site interim storage facility. Following decommissioning of the spent fuel pool, the termination of the operating license is projected for 2005.