Diablo Canyon 1 begins Fall 2026 refueling outage

Started by Core Content, Oct 13, 2026, 06:36

Previous topic - Next topic

0 Members and 0 Guests are viewing this topic.

Core Content

Diablo Canyon 1, Avila Beach, California.

Pacific Gas & Electric began a routine refueling outage at Diablo Canyon 1 on October 11, 2026. The 1,122-megawatt unit started the project one day earlier than its scheduled October 12 start date, targeting a 35-day duration.

Going into this project, the Westinghouse four-loop pressurized water reactor maintained an unscheduled-outage-free streak of 297 days after running about 86 percent of its typical 595-day operating cycle. Its prior 2025 capacity factor reached 88.9 percent, compared to a broader U.S. fleet capacity factor of 81.3 percent across 94 units. Operator Pacific Gas & Electric manages one other nuclear unit in the United States.

AVILA BEACH, CA. Diablo Canyon 1 came offline on Oct 11, 2026 for refueling. The published schedule had a Oct 12, 2026 start; actual is 1 day earlier than planned. Planned outage length is 35 days (back to service around Nov 16, 2026).

NukeWorker's start-date projection scores 100% accuracy for this unit.

Across the U.S. fleet of 94 commercial reactors, today's combined capacity factor is 81.3% (15 units currently refueling, 2 units in unscheduled outages), below the 81.8% baseline for this month over the past five years. At the same site, Diablo Canyon 2 is running at full power. Point Beach 1, Millstone 3, and Peach Bottom 2 also began refueling outages within the past week. With the unit offline for refueling, that takes about 898,000 homes' worth of generation off the grid.

Diablo Canyon 1 is a 1,122-MW Westinghouse 4-loop PWR operated by Pacific Gas & Electric (commercial operation since 1985). The utility operates 1 other U.S. nuclear unit. Its operating license runs through 2064 (renewed in 2026). The unit ran at a 88.9% capacity factor in 2025, a steady year.

Heading to Avila Beach, CA for outage work? Current per-diem averages $177/night lodging plus $86/day meals (total $263/day), and Unemployment Benefits are $450 weekly. See open nuclear jobs in California on NukeWorker.

View Diablo Canyon 1's ratings, history, projections, and current status on NukeWorker.

Want the full picture? Subscribe to the NukeWorker outage schedule for every current and upcoming U.S. nuclear outage.

Sources: NRC Daily Reactor Power Status reports, utility-published outage schedules, and NukeWorker's projections.