Dresden 3, Morris, Illinois.

Dresden 3 completed a routine refueling outage running 7 days longer than the planned 16 days. The 23-day outage lasted from Oct 26, 2026 to Nov 17, 2026 at 0% power, marking the fourth-longest duration among the unit's 15 tracked refuels. The unit returned to full power (100%) as of the NRC report of Nov 23, 2026.

23 days outage · 7 days past schedule · 895 MW back at full power

Dresden 3 completed its Fall 2026 refueling outage, reaching full power on Nov 21, 2026 after 23 days offline. The outage began on Oct 26, 2026. The reactor was critical by the NRC's Nov 18, 2026 report, in Mode 1 by Nov 19, 2026, and back on the grid by Nov 20, 2026. First power to full power took 3 days.

The published schedule had it at 16 days (Oct 27, 2026 to Nov 12, 2026), so the actual ran 7 days longer than planned.

It came off line after a 18-day end-of-cycle coastdown, with output drifting from 95% to 89%.

Counting the 23 days offline and the climb back to full power, the outage cost roughly 536,000 MWh of generation, worth approximately $21 million at recent wholesale prices.

Across the U.S. fleet of 94 commercial reactors, today's combined capacity factor is 91.0% (6 units currently refueling, 3 units in unscheduled outages), above the 88.0% baseline for this month over the past five years. At the same site, Dresden 2 is running at full power. Comanche Peak 1, Palo Verde 1, Prairie Island 1, and Farley 2 also completed refueling outages within the past week.

Dresden 3 is an 895-MW General Electric BWR/3 operated by Constellation Energy (commercial operation since 1971). At full power, it supplies enough electricity for roughly 716,000 homes. The utility operates both units at this site and 19 more at 11 other U.S. plants. Ownership history: Exelon took it over in an October 2000 merger with Commonwealth Edison (Unicom), and Constellation Energy took it over in Exelon's February 2022 spin-off. Its operating license runs through 2051 (renewed in 2025). The unit ran at a 97.8% capacity factor in 2025, one of its strongest years.

View Dresden 3's ratings, history, projections, and current status on NukeWorker.

Want the full picture? Subscribe to the NukeWorker outage schedule for every current and upcoming U.S. nuclear outage.

Sources: NRC Daily Reactor Power Status reports, validated outage schedules, and NukeWorker's projections.