Comanche Peak 1 completes Fall refueling outage in 30 days

Started by Core Content, Today at 06:35

Previous topic - Next topic

0 Members and 0 Guests are viewing this topic.

Core Content

Comanche Peak 1, Glen Rose, Texas.

Comanche Peak 1 completed its routine refueling outage 2 days ahead of the planned 32-day schedule, lasting 30 days from Oct 19, 2026 to Nov 17, 2026. The duration ran 1.9 days below the unit history average of 31.9 days across 18 prior refuels. By the NRC report of Nov 20, 2026, the unit was back at full power at 100%.

30 days outage · 2 days ahead of schedule · 1,209 MW back at full power

After 30 days offline for its Fall 2026 refueling outage, Comanche Peak 1 reached full power on Nov 20, 2026. The outage began on Oct 19, 2026. The reactor was critical by the NRC's Nov 18, 2026 report and back on the grid by Nov 19, 2026. First power to full power took 2 days.

The published schedule had it at 32 days (Oct 18, 2026 to Nov 19, 2026), so the actual ran 2 days shorter than planned.

It came off line after a 9-day end-of-cycle coastdown, with output drifting from 97% to 90%.

Going into the refueling, the unit had run for about 13 months without an unscheduled outage.

Counting the 30 days offline and the climb back to full power, the outage cost roughly 898,000 MWh of generation, worth approximately $36 million at recent wholesale prices.

Across the U.S. fleet of 94 commercial reactors, today's combined capacity factor is 90.5% (6 units currently refueling, 3 units in unscheduled outages), above the 88.0% baseline for this month over the past five years. At the same site, Comanche Peak 2 is running at full power. Dresden 3, Palo Verde 1, North Anna 2, and Salem 1 also completed refueling outages within the past week.

Comanche Peak 1 is a 1,209-MW Westinghouse 4-loop PWR operated by Vistra (commercial operation since 1990). At full power, it supplies enough electricity for roughly 967,000 homes. The utility operates both units at this site and 4 more at 3 other U.S. plants. Ownership history: Luminant (Energy Future Holdings) took it over in an October 2007 buyout of TXU, and Vistra Energy took it over in Luminant's October 2016 spin-off. Its operating license runs through 2050 (renewed in 2024). The unit ran at a 92.4% capacity factor in 2025, a solid year of operation.

View Comanche Peak 1's ratings, history, projections, and current status on NukeWorker.

Want the full picture? Subscribe to the NukeWorker outage schedule for every current and upcoming U.S. nuclear outage.

Sources: NRC Daily Reactor Power Status reports, validated outage schedules, and NukeWorker's projections.