Palo Verde 1 completes Fall refuel in 47 days, caps 510-day B2B run

Started by Core Content, Today at 06:35

Previous topic - Next topic

0 Members and 0 Guests are viewing this topic.

Core Content

Palo Verde 1, Tonopah, Arizona.

Palo Verde 1 completed its routine refueling outage in 47 days, running 2 days longer than the planned 45 days. This duration was 4.6 days above the average of 18 prior refuels and ranks as the sixth-longest among the unit's 19 tracked refuels. The unit, which had operated for more than 3 years without an unscheduled outage prior to this event, returned to 100% power as of the Nov 23, 2026 NRC report.

47 days outage · 2 days past schedule · tenth B2B run complete · 1,311 MW back at full power

Palo Verde 1 completed its Fall 2026 refueling outage, reaching full power on Nov 23, 2026 after 47 days offline. The outage began on Oct 3, 2026. The reactor was critical by the NRC's Nov 19, 2026 report and back on the grid by Nov 20, 2026. First power to full power took 4 days.

The published schedule had it at 45 days (Oct 3, 2026 to Nov 17, 2026), so the actual ran 2 days longer than planned.

It also capped a 510-day breaker-to-breaker run, the unit's tenth qualified B2B run. Going into the refueling, the unit had run for more than 3 years without an unscheduled outage.

Counting the 47 days offline and the climb back to full power, the outage cost roughly 1.52 million MWh of generation, worth approximately $61 million at recent wholesale prices.

Across the U.S. fleet of 94 commercial reactors, today's combined capacity factor is 91.0% (6 units currently refueling, 3 units in unscheduled outages), above the 88.0% baseline for this month over the past five years. At the same site, Palo Verde 2 and Palo Verde 3 are both running at full power. Comanche Peak 1, Dresden 3, Oconee 1, and Watts Bar 2 also completed refueling outages within the past week.

Palo Verde 1 is a 1,311-MW Combustion Engineering System 80 PWR operated by Arizona Public Service (commercial operation since 1986). At full power, it supplies enough electricity for roughly 1 million homes. The utility operates all 3 units at this site and no other U.S. nuclear plant. Its operating license runs through 2045 (renewed in 2011). The unit ran at an 87.8% capacity factor in 2025, a steady year.

View Palo Verde 1's ratings, history, projections, and current status on NukeWorker.

Want the full picture? Subscribe to the NukeWorker outage schedule for every current and upcoming U.S. nuclear outage.

Sources: NRC Daily Reactor Power Status reports, validated outage schedules, and NukeWorker's projections.