Prairie Island 1 returns from Fall refuel, 12 days past schedule

Started by Core Content, Today at 06:35

Previous topic - Next topic

0 Members and 0 Guests are viewing this topic.

Core Content

Prairie Island 1, Welch, Minnesota.

Prairie Island 1 returned to full power at 99% as of the NRC report of Nov 19, 2026, after a routine refueling outage ran 12 days longer than the planned 30 days. The 42-day outage from Oct 3, 2026 to Nov 13, 2026 ran 5.6 days below the unit history average of 47.6 days across 15 prior refuels.

42 days outage · 12 days past schedule · 521 MW back at full power

Prairie Island 1 completed its Fall 2026 refueling outage, reaching full power on Nov 19, 2026 after 42 days offline. The outage began on Oct 3, 2026. The reactor was critical by the NRC's Nov 14, 2026 report and back on the grid by Nov 18, 2026. First power to full power took 5 days.

The published schedule had it at 30 days (Oct 2, 2026 to Nov 1, 2026), so the actual ran 12 days longer than planned.

The outage ran about 6 days shorter than the unit's 15-cycle average of 47.6 days. Going into the refueling, the unit had run for about 15 months without an unscheduled outage.

Counting the 42 days offline and the climb back to full power, the outage cost roughly 562,000 MWh of generation, worth approximately $22 million at recent wholesale prices.

Across the U.S. fleet of 94 commercial reactors, today's combined capacity factor is 88.4% (6 units currently refueling, 3 units in unscheduled outages), above the 88.0% baseline for this month over the past five years. At the same site, Prairie Island 2 is running at full power. Farley 2, Robinson 2, Comanche Peak 1, and Dresden 3 also completed refueling outages within the past week.

Prairie Island 1 is a 521-MW Westinghouse 2-loop PWR operated by Xcel Energy (commercial operation since 1973). At full power, it supplies enough electricity for roughly 417,000 homes. The utility operates both units at this site and 1 more at another U.S. plant. Ownership history: Nuclear Management Co took over running it from Northern States Power in August 2000, and Xcel Energy took over running it from Nuclear Management Co in September 2008. Its operating license runs through 2033 (renewed in 2011). The unit ran at a 92.1% capacity factor in 2025, a solid year of operation.

View Prairie Island 1's ratings, history, projections, and current status on NukeWorker.

Want the full picture? Subscribe to the NukeWorker outage schedule for every current and upcoming U.S. nuclear outage.

Sources: NRC Daily Reactor Power Status reports, validated outage schedules, and NukeWorker's projections.