Farley 2 returned to 100% power by Nov 16, 2026, following a routine refueling outage that finished 2 days early. The outage lasted 25 days, coming in 14.9 days below the average of the unit's 18 prior refuels which averaged 39.9 days. Going into this refuel, the unit had spent about 16 months without an unscheduled outage.

25 days outage · 2 days ahead of schedule · seventh B2B run complete · 896 MW back at full power

Farley 2 completed its Fall 2026 refueling outage, reaching full power on Nov 15, 2026 after 25 days offline. The outage began on Oct 19, 2026. The reactor was critical by the NRC's Nov 13, 2026 report and back on the grid by Nov 14, 2026. First power to full power took 2 days.

The published schedule had it at 27 days (Oct 18, 2026 to Nov 14, 2026), so the actual ran 2 days shorter than planned.

The outage ran about 15 days shorter than the unit's 18-cycle average of 39.9 days. It also capped a 476-day breaker-to-breaker run, the unit's seventh qualified B2B run. Going into the refueling, the unit had run for about 16 months without an unscheduled outage.

Counting the 25 days offline and the climb back to full power, the outage cost roughly 567,000 MWh of generation, worth approximately $23 million at recent wholesale prices.

Across the U.S. fleet of 94 commercial reactors, today's combined capacity factor is 85.6% (9 units currently refueling, 3 units in unscheduled outages), below the 88.0% baseline for this month over the past five years. At the same site, Farley 1 is running at full power. Robinson 2, Prairie Island 1, Palo Verde 1, and Salem 1 also completed refueling outages within the past week.

Farley 2 is an 896-MW Westinghouse 3-loop PWR operated by Southern Nuclear (commercial operation since 1981). At full power, it supplies enough electricity for roughly 717,000 homes. The utility operates both units at this site and 6 more at 2 other U.S. plants. Its operating license runs through 2041 (renewed in 2005). The unit ran at a 74.0% capacity factor in 2025, with some downtime through the year.

View Farley 2's ratings, history, projections, and current status on NukeWorker.

Want the full picture? Subscribe to the NukeWorker outage schedule for every current and upcoming U.S. nuclear outage.

Sources: NRC Daily Reactor Power Status reports, validated outage schedules, and NukeWorker's projections.