Robinson 2 caps first B2B run with 40-day Fall refuel

Started by Core Content, Today at 06:36

Previous topic - Next topic

0 Members and 0 Guests are viewing this topic.

Core Content

Robinson 2, Hartsville, South Carolina.

Robinson 2 completed a routine refueling outage on Nov 11, 2026, running 10 days longer than the planned 30 days. Despite the schedule variance, the 40-day duration was 5.9 days below the average of 45.9 days for the unit's 16 prior refuels. The unit returned to 100% power by Nov 16, 2026, following a period of more than 3 years without an unscheduled outage.

40 days outage · 10 days past schedule · first B2B run complete · 759 MW back at full power

After 40 days offline for its Fall 2026 refueling outage, Robinson 2 reached full power on Nov 16, 2026. The outage began on Oct 3, 2026. The reactor was critical by the NRC's Nov 12, 2026 report and back on the grid by Nov 13, 2026. First power to full power took 4 days.

The published schedule had it at 30 days (Oct 9, 2026 to Nov 8, 2026), so the actual ran 10 days longer than planned.

It came off line after a 9-day end-of-cycle coastdown, with output drifting from 97% to 91%.

The outage ran about 6 days shorter than the unit's 16-cycle average of 45.9 days. It also capped a 666-day breaker-to-breaker run, the unit's first qualified B2B run. Going into the refueling, the unit had run for more than 3 years without an unscheduled outage.

Counting the 40 days offline and the climb back to full power, the outage cost roughly 754,000 MWh of generation, worth approximately $30 million at recent wholesale prices.

Across the U.S. fleet of 94 commercial reactors, today's combined capacity factor is 85.6% (9 units currently refueling, 3 units in unscheduled outages), below the 88.0% baseline for this month over the past five years. Farley 2, Prairie Island 1, Diablo Canyon 1, and Salem 1 also completed refueling outages within the past week.

Robinson 2 is a 759-MW Westinghouse 3-loop PWR operated by Duke Energy (commercial operation since 1971). At full power, it supplies enough electricity for roughly 607,000 homes. The utility operates 10 other U.S. nuclear units at 5 other plants. Ownership history: Progress Energy took it over in a November 2000 merger with Carolina Power & Light, and Duke Energy took it over in a July 2012 merger with Progress Energy. Its operating license runs through 2050 (renewed in 2026). The unit ran at a 99.5% capacity factor in 2025, one of its strongest years.

View Robinson 2's ratings, history, projections, and current status on NukeWorker.

Want the full picture? Subscribe to the NukeWorker outage schedule for every current and upcoming U.S. nuclear outage.

Sources: NRC Daily Reactor Power Status reports, validated outage schedules, and NukeWorker's projections.